
1 | |
---|---|
Project:Residential Houses | Location: Wario south rd. Karen, Nairobi |
Client: Taita Villas Development | Architect: Karago & Associates |
Quantity Surveyor: Armstrong and Duncan | Structural Engineer: Interconsult Engineers |
Project Duration: 14 months | Project’s Financier: Hon Mjr rtd. Marsden Madoka |
Commencement (Month/Year):February 2009 | Completion Date (Month/Year):April 2011 |
Name of Other Consultants, if any:Maiteri and Associates | General Remarks: ( Complete) |
Narrative Description of Project: 8 No. Town House with associated external works |
2 | |
---|---|
Project:Partitions to Office and Class rooms | Location: ERETO PLAZA, Nakuru |
Client: Kenya Institute of Management | Architect: Elite Project Managers |
Quantity Surveyor: Elite QuantitySurveyors | Structural Engineer: - |
Project Duration: 2 months | Project Financiers: Kenya Institute of Management |
Commencement (Month/Year):August 2010 | Completion Date (Month/Year):September 2010 |
Name of other Consultants, if any: | General Remarks: Completed |
Narrative Description of Project: Partitions to Offices and Classrooms for KIM Nakuru 3 |
3 | |
---|---|
Project:Diatev Apartments | Location: Kangemi Gichagi maumau |
Client: Kamau ngotho. | Architect:Planoconsult Architects |
Quantity Surveyor: Construction Costs Consultancy | Structural Engineer:: Baseplan Consulting Engineers |
Project Duration: 54 Wks | Project Financiers: Kamau Ngotho |
Commencement (Month/Year):May 2009 | Completion Date (Month/Year):June 2010 |
Name of Other Consultants, if any: - | General Remarks: Completed |
Narrative Description of Project: 24 No. Apartments with associated External Works |
4 | |
---|---|
Project: Construction of a Warehouse | Location: Mogadishu Sea Port |
Client: UNWFP Somalia | Architect: East Africa Modern Engineering Co. (EAMECO) |
Quantity Surveyor: (EAMECO) | Structural Engineer: (EAMECO) |
Project Duration: 12months | Project Finaciers: JICA |
Commencement (Month/Year): Feb 2009 | Completion Date (Month/Year): Feb, 2010 |
Name of Other Consultants, if any:UNWFP head Office, UNOPS | General Remarks: Complete |
Narrative Description of Project: Warehouse, Office Block and associated external Works |
5 | |
---|---|
Project: Proposed Eassy Fibre Landing Station Mogadishu | Location: Mogadishu Airport |
Client: Dalkom Somalia | Architect: Oracle Architects |
Quantity Surveyor: Span Management | Structural Engineer: |
Project Duration: 52wks | Financiers: World Bank |
Commencement (Month/Year): Feb, 2013 | Completion Date (Month/Year): Jan, 2014 |
Name of Other Consultants, if any:Frontier Optical Network | General Remarks: Completed |
Narrative Description of Project: Construction of a office block 2 No. Storey with associated external works, Excavation and laying of land cable 2Km away |
6 | |
---|---|
Project:12No. Apartments | Location: Lower Kabete Lane, Spring Valley, Nairobi, Kenya |
Client: SSSD Temple | ArchitectPlanners de Morderne |
Quantity Surveyor: Gakuya and Associated | Structural Engineer: Civil Eng. Design (K) Ltd |
Project Duration: 12months | |
Commencement (Month/Year):June 2010 | Completion Date (Month/Year): July 2011 |
Name of Other Consultants, if any: | General Remarks: Complete |
Narrative Description of Project: Labour Sub-Contractor |
7 | |
---|---|
Project:Office Rehabilitation and Alterations | Location: 3rd Floor Transnational Plaza |
Client: Urban Centre International | ArchitectPlanoConsult |
Quantity Surveyor: - | Structural Engineer: - |
Project Duration: 3 months | |
Commencement (Month/Year):January 2009 | Completion Date (Month/Year):April 2009 |
Name of Other Consultants, if any: | General Remarks: Completed |
Narrative Description of Project: Demolisions, Granito tilling, Partitioning, and supply of furniture |
8 | |
---|---|
Project:Proposed Church Hall | Location: Kasarani Nairobi |
Client: St. Francis CHurch | ArchitectEmplan Designs |
Quantity Surveyor: Austin Kamau Quantity Surveyors | Structural Engineer: Maina and Associates |
Project Duration: 12months | |
Commencement (Month/Year):June 2009 | Completion Date (Month/Year): July 2010 |
Name of Other Consultants, if any: | General Remarks: Complete |
Narrative Description of Project: Construction of a church hall with offices and associated external works |
9 | |
---|---|
Project:Class Renovations and Partitions to Kenya Institute of Management | Location: Emperor Plaza Kenyatta Avenue Nairobi |
Client: Kenya Institute of Management | ArchitectElite Project Managers |
Quantity Surveyor: Elite Project Managers | Structural Engineer: - |
Project Duration: 2 Weeks | |
Commencement (Month/Year):December 2010 | Completion Date (Month/Year):December 2010 |
Name of Other Consultants, if any: | General Remarks: Complete |
Narrative Description of Project: Demolisions, Tiling and Partitionning to classes 5. No. Floors |
10 | |
---|---|
Project:Renovations to Hazina Sacco | Location: Ngong Road |
Client: Hazina Sacco | ArchitectPlano Consult |
Quantity Surveyor: Austine Kamau Quantity Surveyors | Structural Engineer: Civil Eng. Design (K) Ltd |
Project Duration: 2months | |
Commencement (Month/Year):June 2010 | Completion Date (Month/Year): July 2011 |
Name of Other Consultants, if any: | General Remarks: Complete |
Narrative Description of Project: Additional Banking Hall and FOSA Offices |